Chief Minister, Treasury and Economic Development Directorate (CMTEDD)

Suppliers to Government
Please be advised that, from 1 July 2015, the ACT Government will be publishing relevant information about invoices it has paid for goods, services or works it has received. Invoices with a value of $25,000 or more will be known as Notifiable Invoices and information about the invoices will be published on the Notifiable Invoices Register. This Register will be located on the procurement website and updated monthly.  More information on Notifiable Invoices is available from ACT Government Notifiable Invoices Register
Project and Description Procurement Branch

Total Investment

Expected Prequalification Category Estimated Call Consultancy Estimated Call Construction Last Updated

Public Housing Renewal Block 17, Section 73 Nicholls
Construction. Construction of 14 Supportive Housing Properties.
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2015/03

Public Housing Renewal Taskforce  $5,068,000     ON HOLD pending ACAT appeal 07/09/2015FF 

Public Housing Renewal Block 1-14, Section 13 & 14  Moncrieff
Design and Construction of 28 adjoining townhouse in clusters of 14 over two sections
Project Officer: Ken Williams
Funding: Public Housing Renewal HR2015/04 -05

Public Housing Renewal Taskforce  $10,976,000     August 2015  15/07/2015FF

Public Housing Renewal Block , 12 Section 52 Holt
Construction 12 units in a multi unit site
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2016/01

Public Housing Renewal Taskforce$4,344,000 PHRT Completed31/3/2017FF

Public Housing Renewal, Part Block 2 Section 28 Greenway
Construction of 26 townhouses on a multi unit site
Project Officer: Greg Burghart
Funding: Public Housing Renewal HR2016/02

Public Housing Renewal Taskforce$9,412,000 PHRT May 201731/3/2017FF

Public Housing Renewal, Block 45 Section 100 Narrabundah
Construction of 12-25 dwellings
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2016/04

Public Housing Renewal Taskforce$4,344,000 PHRT February 201731/3/2017FF

Public Housing Renewal, Block TBC Section 17 Throsby
Construction of 24 units on a multi unit site
Project Officer: Greg Burghart
Funding: Public Housing Renewal HR2016/05

Public Housing Renewal Taskforce$8,688,000 PHRT August 201731/3/2017FF

Public Housing Renewal Block 2, Section 60 Throsby
Construction 25 units on a multi unit site
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2016/06

Public Housing Renewal Taskforce$9,050,000 PHRT May 201731/3/2017FF

Public Housing Renewal, Various Blocks and Sections Throsby
Design and Construction of 8 detached dwellings
Project Officer: Ben Wise
Funding: Public Housing Renewal HR2016/07B

Public Housing Renewal Taskforce$3,160,000CR-F1 Panel Contract March 201722/6/2016FF

Public Housing Renewal, Various Blocks and Sections Throsby
Design and Construction of 10 detached dwellings
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2016/07C

Public Housing Renewal Taskforce$2,896,000 PHRT May 201731/3/2017FF

Public Housing Renewal Block , Section 10 Greenway
Construction of 30 dwellings on a multi unit site
Project Officer: Rajah Sivakumar
Funding: Public Housing Renewal HR2016/08

Public Housing Renewal Taskforce$10,860,000 PHRT December 201731/7/2017FF

Public Housing Renewal Block , Various Blocks and Sections Denman Prospect
Construction 12 residential dwellings
Project Officer: Rajah Sivakumar
Funding: Public Housing Renewal HR2016/09

Public Housing Renewal Taskforce$4,340,000PHRT Completed31/3/2017FF

Public Housing Renewal Block , Various Blocks and Sections Denman Prospect
Design and Construction 6 residential dwellings
Project Officer: Rajah Sivakumar
Funding: Public Housing Renewal HR2016/10A

Public Housing Renewal Taskforce$2,170.000 PHRT completed31/3/2017FF

Public Housing Renewal Block , Various Blocks and Sections Denman Prospect
Design and Construction 6 residential dwellings
Project Officer: Rajah Sivakumar
Funding: Public Housing Renewal HR2016/10B

Public Housing Renewal Taskforce$2,170,000 PHRT Completed31/7/2017FF

Public Housing Renewal Block , Block 16 Section 99 Holt
Construction 24 units
Project Officer: Greg Burghart
Funding: Public Housing Renewal HR2016/22B

Public Housing Renewal Taskforce$8,688,000 PHRT July 201731/3/2017FF

Public Housing Renewal Block , 2 Section 20 Monash
Construction of 6 Supportive Housing Dwellings
Project Officer: Greg Burghart
Funding: Public Housing Renewal HR2016/31

Public Housing Renewal Taskforce$2,172,000PHRT May 201731/3/2017FF

Public Housing Renewal Block , BB Section Ba Gungahlin

Project Officer: TBA
Funding: Public Housing Renewal HR2017/02

Public Housing Renewal Taskforce$13,394,000PHRT May 201731/3/2017FF

Public Housing Renewal Block , 1 Section 29 Wright
Construction of 32 Supportive Housing Units
Project Officer: TBA
Funding: Public Housing Renewal HR2017/03

Public Housing Renewal Taskforce $11,584,000 PHRT  June 201731/3/2017FF 

Public Housing Renewal Block , 1 Section 45 Chapman
Construction of 29 Supportive Housing Units
Project Officer: TBA
Funding: Public Housing Renewal HR2017/04

Public Housing Renewal Taskforce$10,498,000  PHRT June 201731/3/2017FF

Public Housing Renewal, Block 59 Section 39 Taylor
Construction of 26 Units and 10 Townhouses
Project Officer: TBA
Funding: Public Housing Renewal HR2018/03

Public Housing Renewal Taskforce $13,032,000PHRT  September 2017 31/3/2017FF

Public Housing Renewal, Block 3 Section 37 Taylor
Construction of 32 Units and 10 Townhouses
Project Officer: Rajah Sivakumer
Funding: Public Housing Renewal HR2018/04

 Public Housing Renewal Taskforce$13,032,000 PHRT  May 201731/3/2017FF

Public Housing Renewal, Block 1 Section 20 Taylor
Construction of 5 Townhouses
Project Officer: TBA
Funding: Public Housing Renewal HR2018/05

Public Housing Renewal Taskforce $1,810,000 PHRT June 201731/3/2017FF

Public Housing Renewal, Block 5 Section 23 Taylor
Construction of 6 Townhouses
Project Officer: TBA
Funding: Public Housing Renewal HR2018/06

Public Housing Renewal Taskforce $2,172,000PHRT August 2017 31/3/2017FF 

Public Housing Renewal Various Single Residential Dwellings Taylor
Design and Construction of 4 Residential Dwellings
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2018/07

Public Housing Renewal Taskforce$1,448,000PHRT  July 2017 31/3/2017FF

Public Housing Renewal Various Single Residential Dwellings Taylor
Design and Construction of 6 Residential Dwellings
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2018/08

Public Housing Renewal Taskforce  $2,172,000PHRT August 201731/3/2017FF

Public Housing Renewal Various Single Residential Dwellings Taylor
Design and Construction of 4 Residential Dwellings
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2018/09

Public Housing Renewal Taskforce$1,448,000 PHRT August 201731/3/2017FF

Public Housing Renewal Various Single Residential Dwellings Taylor
Design and Construction of 12 Residential Dwellings
Project Officer: Sean Richards
Funding: Public Housing Renewal HR2018/10

Public Housing Renewal Taskforce$4,344,000 PHRT October 2017 31/3/2017FF

Public Housing Renewal Block , 2 Section 21 Holder
Construction of 30 Supportive Housing Units
Project Officer: TBA
Funding: Public Housing Renewal HR2018/11

Public Housing Renewal Taskforce $10,860,000PHRT June 201731/3/2017FF 

Public Housing Renewal Block , 29 Section 36 Mawson
Construction of 11 Supportive Housing Dwellings
Project Officer: TBA
Funding: Public Housing Renewal HR2018/13

Public Housing Renewal Taskforce $3,982,000PHRT  June 201731/3/2017FF

Manuka Oval Broadcast and Media Centre Project
PCW Project Officer: Rebecca Power
Project No. 28803.110

Civil Infrastructure$TBACB F10 April 20173/3/2017RP

Phillip Oval upgrade
* Sourced from Appendix D Capital Works - New Initiatives by Type 2015-16 Budget Paper No.3
LDA Project Officer: Peter Rea
Project No. 27367.100

Civil Infrastructure $4,613,000     17/12/2015GL
CICW - Better Roads for Gungahlin
Horse Park Drive pedestrian overpass (feasibility study for Moncrieff to Taylor (North Gungahlin School) bridge)
Project Officer: Joanne Makela
Project Number: Treasury Finance Project No 54795
Funding Source: 2015 - 16 Budget Paper No. 3
Civil Infrastructure$400,000  TBA Completed 21/11/2016McG
CICW - Better Roads for Gungahlin
Gungahlin Town centre road network (construction of Ernest Cavanagh St extension) 
Project Officer: Brook Milne
Project Number: Treasury Finance Project No 54794
Funding Source: 2015 - 16 Budget Paper No. 3
Civil Infrastructure$4,500,000TBA  January 201721/11/2016McG
CICW - Better Roads for Inner South – Yarralumla Estate (Canberra Brickworks Roads Feasibility Study)
Project Officer: Joanne Makela
Project Number: Treasury Finance Project No. 54796
Funding Source:  2015 - 16 Budget Paper No. 3
Civil Infrastructure$250,000CE Completed 21/11/2016McG
CICW - Improving Our Suburbs – New Molonglo Valley Infrastructure
Construction of John Gorton Dr arterial road and two intersections
Project Officer: Misha Beljic
Project Number: Treasury Finance Project No. 54797
Funding Source: 2015 - 16 Budget Paper No. 3
Civil Infrastructure$22,370,000F20, R4 December 201621/11/2016McG

CICW - Improving Our Suburbs – New Molonglo Valley Infrastructure - Construction of water and sewer main and SW creek remediation
CICW - Improving our Suburbs - New Molonglo Valley Infrastructure - Construction of:
1. water main - D and C
2. sewer main - by LDA
3. SW pond
4. Deep Creek protection works (temporary - by LDA)Project Officer: Brad Smith 
Project Number: Treasury Finance Project No. 54798
Funding Source: 2015 - 16 Budget Paper No. 3

Civil Infrastructure$10,100,000TBA December 201621/11/2016McG
CICW - Improving Our Suburbs – New Molonglo Valley Infrastructure - Procurement options and delivery method study for John Gorton Dr and Molonglo River bridge
Project Officer: Misha Beljic
Project Number: Treasury Finance Project No. 54800
Funding Source: 2015 - 16 Budget Paper No. 3
Civil Infrastructure$250,000 December 2016 21/11/2016McG
CICW - Securing Electricity Supply in the ACT
Second supply network at various locations
Project Officer: Brad Smith
Project Number: Treasury Finance Project No. 54801
Funding Source: 2015 - 16 Budget Paper No. 3 
Civil Infrastructure$500,000 Completed 21/11/2016McG
CICW - Caring for Our Environment - Lake Tuggeranong Water Quality Improvement Stage 2
(Isabella Weir continued construction funding)
Project Officer: Richard Toomey
Project Number: Treasury Finance Project No. 54802
Funding Source: 2015 - 16 Budget Paper No. 3
Civil Infrastructure$15,100,000 B3, R4 F15Completed 21/11/2016McG